(1)

Where—

(a)

the authority has accepted a proposal notice under regulation 10;

(b)

the Secretary of State has determined that the proposal notice should be accepted under regulation 12(2) or regulation 13; or

(c)

the authority has not lodged an application with the Secretary of State for a determination under regulation 13 within 21 days of receipt of the acknowledgement of service by the tenant group

the tenant group may proceed to prepare a feasibility study.

(2)

The feasibility study must set out—

(a)

confirmation that the houses and area to which to which the feasibility study relates are those specified in the proposal notice;

(b)

the possible options for the disposal of the houses and area specified in the proposal notice to a PRP (in particular whether to an existing PRP or a new PRP); and

(c)

the feasibility of each option.