Paragraph 6 Procedure for funding route 1 cases to provide, improve and adapt units
A local authority shall ensure that, in a case where it determines that funding route 1 applies, a grant applicant submits to that local authority a programme proposal report in terms satisfactory to, and in a form to be specified by, that local authority, detailing–
all proposed HAG projects to be undertaken by the grant applicant for a period up to 3 years;
the design and specification standards the grant applicant seeks to achieve for each project; and
the grant applicant’s policies and procedures for managing procurement processes to ensure that the standards in sub-paragraph (1)(b) above are achieved.
Following receipt and appraisal of a programme proposal report, a local authority may issue a programme agreement indicating the amount of HAG that it may make available to a grant applicant over a period of up to 3 years which programme agreement shall specify–
target outputs;
HAG subsidy target; and
project locations.
Once a programme agreement has been issued, the local authority shall ensure in relation to each project that a grant applicant submits in such terms as that local authority considers satisfactory–
at acquisition stage, a report using the form to be specified by that local authority and at settlement the form to be specified by that local authority;
at cost plan stage, where that local authority considers necessary, a report using the form to be specified by that local authority; and
at tender stage, a report using the form to be specified by that local authority.