# The Housing (Scotland) Act 2001 (Assistance to Registered Social Landlords and Other Persons) (Grants) Regulations 2004, Paragraph 9: Recovery of sums based on the actual cashflow


Where the grant calculated by the local authority using the actual cashflow following receipt of the post completion return is less than the amount of grant specified in the offer of grant (which is calculated using the approved cashflow), 50% of the difference in these two amounts shall be paid by the grant recipient to that local authority within 14 days of ascertainment by that local authority that a repayment of grant is due.

---