  "heading": "Extension of period for completion of work or demolition",
  "text": "(1) The local authority may, at any time, extend the period within which any—\n(a) work required by a work notice, or\n(b) demolition required by a demolition notice,\nmust be completed by such period as it considers reasonable.\n(2) But such a period may be extended only where the local authority—\n(a) considers that satisfactory progress has been made in carrying out the work or demolition, or\n(b) has received a written undertaking from the owner stating that the work or demolition will be completed by a later date which the authority considers satisfactory.\n(3) The local authority must give notice of any extension in accordance with section 62.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "S. 34 in force at 1.4.2009 by S.S.I. 2009/122, art. 3"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/asp/2006/1/section/34",
    "retrieved_at": "2026-10-29T20:16:19.148871+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}