Paragraph 2

Original text. Later amendments are not shown.

(1)

Before commencing the construction of a tidal work the Company shall furnish to A.B. Ports for its approval, which it shall not unreasonably withhold, plans of the work showing the general mode of construction; and that such works

(a)

shall not be constructed otherwise than in accordance with such plans as may be approved by A.B. Ports or as may be determined as hereinafter provided, and

(b)

shall be executed to the reasonable satisfaction of A.B. Ports.

(2)

When submitting plans to the Secretary of State pursuant to article 12 of this Order, the Company shall

(a)

send a copy of those plans to A.B. Ports, and

(b)

on receipt of approval of plans or of any conditions or restrictions imposed by the Secretary of State, send a copy to A.B. Ports.

(3)

In the event of A.B. Ports failing to express its disapproval of any plans within 56 days after they have been delivered to it under this paragraph, it shall be deemed to have approved them.