# The Humber Sea Terminal (Phase III) Harbour Revision Order 2006, Paragraph 4


(1) Subject to sub-paragraph (2), any specified work, approved under paragraph 3, and all protective works required by the Agency under paragraph 3, shall be constructed—
(a) within such reasonable period (if any) as the Agency may approve at the time of approval or upon an application by the Company thereafter (such approval not to be unreasonably withheld);
(b) in accordance with the plans approved or deemed to have been approved or settled under this Schedule; and
(c) to the reasonable satisfaction of the Agency;
and the Agency shall be entitled by its officer to watch and inspect the construction of such works.
(2) The Company shall give to the Agency not less than 14 days’ prior notice in writing of the commencement of construction of any specified work and notice in writing of its completion not later than 7 days after the date thereof.
(3) If any part of the works comprising a structure in, over or under a watercourse is constructed otherwise than in accordance with the requirements of this Part of this Schedule, the Agency may by notice in writing require the Company at the Company’s own expense to comply with the requirements of this Part of this Schedule or (if the Company so elects and the Agency in writing consents, such consent not to be unreasonably withheld) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent as the Agency reasonably requires.
(4) Subject to sub-paragraph (5), if within a reasonable period, being not less than 28 days from the date when a notice under sub-paragraph (3) is served upon the Company, the Company has failed to begin taking steps to comply with the reasonable requirements of the notice and thereafter to complete them within such reasonable period as may be specified in such notice, the Agency may take the steps specified in the notice and may recover the reasonable costs of doing so from the Company.
(5) In the event of any dispute as to whether sub-paragraph (4) is properly applicable to any work in respect of which notice has been served under sub-paragraph (3), or as to the reasonableness of any requirement of such a notice, the Agency shall not except in emergency exercise the powers conferred by sub-paragraph (4) until the dispute has been finally determined.

---
Source: https://www.legislation.gov.uk/uksi/2006/2604/schedule/1/part/2/paragraph/4 (the official version)
Page: https://openlegislation.uk/humber-sea-terminal-phase-iii-harbour-revision-order-2006/schedule-1/part-2/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.