# The HyNet Carbon Dioxide Pipeline Order 2024, Paragraph 109: Access

Extent: E+W+S

If in consequence of the agreement reached in accordance with paragraph 101(1) or the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable SP Manweb to maintain or use the apparatus no less effectively than was possible before such obstruction.

---