# The HyNet Carbon Dioxide Pipeline Order 2024, Paragraph 183: Rights of access – Ash Road (South)

Extent: E+W+S

Subject to Paragraph 184 (Rights of Access – Abnormal Loads), the undertaker must use the entrance from Ash Road as the primary access route (over Plots 1-06, 1-06a, 1-06b and 1-06c as identified on the Land Plans) for construction activities within Plots 1-20, 1-21 and 1-22. Provided that Encirc has granted to the undertaker a suitable right of access across a fit for purpose access route (to the undertaker’s satisfaction) to all of Plot 1-22 as identified on the Land Plans as required by the undertaker—
(a) The undertaker may in relation to Plot 1-21 exercise its powers under article 35 (temporary use of land for carrying out the authorised development) for the purpose of temporary use as a construction working area and for access only; and
(b) The undertaker may not exercise the powers conferred under article 27 (compulsory acquisition of rights and restrictive covenants) in relation to Land Plans Plot 1-21 without the prior consent in writing of Encirc.

---
Source: https://www.legislation.gov.uk/uksi/2024/436/schedule/10/paragraph/183 (the official version)
Page: https://openlegislation.uk/hynet-carbon-dioxide-pipeline-order-2024/schedule-10/paragraph-183
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.