# The HyNet Carbon Dioxide Pipeline Order 2024, Paragraph 274: Retained Apparatus and Alternative Apparatus: protection

Extent: E+W+S

Where reasonably required by either party, in view of the complexity of any proposed works, timescales, phasing or costs, the parties must with due diligence and good faith negotiate a works agreement for the carrying out of Protective Works or the installation of Alternative Apparatus.

---
Source: https://www.legislation.gov.uk/uksi/2024/436/schedule/10/paragraph/274 (the official version)
Page: https://openlegislation.uk/hynet-carbon-dioxide-pipeline-order-2024/schedule-10/paragraph-274
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.