# The HyNet Carbon Dioxide Pipeline Order 2024, Paragraph 282: Retained Apparatus and Alternative Apparatus: protection

Extent: E+W+S

In this Part of this Schedule, “emergency works” means works whose execution at the time when they are executed is required in order to put an end to, or to prevent the occurrence of, circumstances then existing or imminent (or which the person responsible for the works believes on reasonable grounds to be existing or imminent) which are likely to cause danger to persons or property.

---
Source: https://www.legislation.gov.uk/uksi/2024/436/schedule/10/paragraph/282 (the official version)
Page: https://openlegislation.uk/hynet-carbon-dioxide-pipeline-order-2024/schedule-10/paragraph-282
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.