# The HyNet Carbon Dioxide Pipeline Order 2024, Paragraph 296: Co-operation and reasonableness

Extent: E+W+S

Where Apparatus is required to be protected, altered, diverted or removed under this Schedule, the undertaker must use all reasonable endeavours to co-ordinate the execution of any works under this Schedule—
(a) in the interests of safety;
(b) 47.2 in the interest of the efficient and economic execution of both Exolum’s works and the Authorised Development; and
(c) 47.3 taking into account the need to ensure the safe and efficient operation of Apparatus and carrying out of Exolum’s functions.

---