# The HyNet Carbon Dioxide Pipeline Order 2024, Paragraph 301: Emergency circumstances

Extent: E+W+S

The parties agree to act in good faith and in all reasonableness to agree any revisions to any schedule, programme or costs estimate (which will include costs of demobilising and remobilising any workforce, and any costs to protect the Apparatus “mid-works”) to account for the suspension.

---