# The HyNet Carbon Dioxide Pipeline Order 2024, Paragraph 97: Capitalised sums

Extent: E+W+S

Any capitalised sum which is required to be paid under this Part must be calculated by multiplying the reasonable cost of the maintenance or renewal works to the waterway necessitated as a result of the operation of the authorised development by the number of times that the maintenance or renewal works will be required during the operation of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2024/436/schedule/10/paragraph/97 (the official version)
Page: https://openlegislation.uk/hynet-carbon-dioxide-pipeline-order-2024/schedule-10/paragraph-97
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.