# The HyNet Carbon Dioxide Pipeline Order 2024, Paragraph 17: Provision of ‘as built’ details

Extent: E+W+S

The undertaker must, within 3 months of the completion of the authorised development, provide to the relevant planning authorities details of—
(a) the location and depth of each part of the Pipeline as it has been constructed;
(b) any protective measures in place over any part of the Pipeline; and
(c) the locations of pipeline markers.

---