# The HyNet Carbon Dioxide Pipeline Order 2024, Paragraph 18: Restoration of land

Extent: E+W+S

Subject to article 34 (temporary use of land for carrying out the authorised development), any land within the Order limits which is used temporarily for or in connection with construction must be reinstated to a condition fit for its former use, or such other condition as the relevant planning authority may approve, within 12 months of completion of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2024/436/schedule/2/paragraph/18 (the official version)
Page: https://openlegislation.uk/hynet-carbon-dioxide-pipeline-order-2024/schedule-2/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.