# The HyNet Carbon Dioxide Pipeline Order 2024, Part 1: Streets subject to permanent street works

Extent: E+W+S

(1) Area
(2) Streets subject to street works
(3) Description of the street works
In the Borough of Cheshire West and Chester
Private roads being Grinsome Road, Perimeter Road and Elton Lane, Ash Road and unnamed road off Ash Road
Works for the installation and maintenance of access for Work No. 3 between the points marked 1-AA on sheet 1a and the points marked 1-A and 1-B and 1-C, 1-CC and 1-D on sheet 1 of the access rights of way plans
In the Borough of Cheshire West and Chester
Ince Lane
Works for the installation and maintenance of access for Work No. 5 between the points marked 2-G and 2-H on sheet 2 of the access rights of way plans
In the Borough of Cheshire West and Chester
Private roads being unnamed road off Pool Lane
Works for the installation and maintenance of access for Work No. 10 between points marked 3-D and 3-E on sheet 3 of the access and rights of way plans
In the Borough of Cheshire West and Chester
Wervin Road
Works for the installation and maintenance of access for Work No. 17 between points marked 7-D and 7-E on sheet 7 of the access and rights of way plans
In the Borough of Cheshire West and Chester
Station Road
Works for the installation and maintenance of access for Work Nos. 25 and 25A between points marked 10-AA and 10-BB on sheet 10 of the access and rights of way plans
In the County of Flintshire
Sealand Road
Works for the installation and maintenance of access for Work Nos. 30 and 30B between points marked 12-E and 12-F on sheet 12 of the access and rights of way plans
In the County of Flintshire
Deeside Lane
Works for the installation and maintenance of access for Work Nos. 30C and 31 between points marked 12-DD on sheet 12 and 13-AA on sheet 13 of the access and rights of way plans
In the County of Flintshire
Private road off B5129 (Flint Road)
Works for the installation and maintenance of access for Work No. 31B between points marked 14-I and 14-J on sheet 14 of the access and rights of way plans
In the County of Flintshire
Private road off Gladstone Way
Works for the installation and maintenance of access for Work Nos. 35 and 35A between points marked 16-M and 16-N on sheet 16 of the access and rights of way plans
In the County of Flintshire
Holywell Road
Works for the installation and maintenance of access for Work Nos. 41 and 41C between points marked 18-KK and 18-JJ on sheet 18 of the access and rights of way plans
In the County of Flintshire
Alt-Goch Lane
Works for the installation and maintenance of access for Work Nos. 48 and 49 between points marked 22-K and 22-L on sheet 22 of the access and rights of way plans

---
Source: https://www.legislation.gov.uk/uksi/2024/436/schedule/3/part/1 (the official version)
Page: https://openlegislation.uk/hynet-carbon-dioxide-pipeline-order-2024/schedule-3/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.