# The HyNet Carbon Dioxide Pipeline Order 2024, Part 2: Public rights of way to be stopped up

Extent: E+W+S

Area
(2) Public right of way
(3) Extent of Stopping up
(4) Alternative route
In the County of Flintshire
Footpath 414/39A
Between the points marked 19-D and 19-DD on sheet 19 of the access and rights of way plans shown with a dashed purple line
Between the points marked 19-D and 19-DD on sheet 19 of the access and rights of way plans

---