# The HyNet Carbon Dioxide Pipeline Order 2024, Part 1: Land of which only temporary possession may be taken

Extent: E+W+S

(1) Area
(2) Number of plot shown on land plans
(3) Purpose for which temporary possession may be taken
(4) Relevant part of authorised development
Cheshire and Chester West
1-05
Temporary use as a construction working area and for access (as part of Work No.3)
Work Nos 1, 2, 3, 3A, 3B 4 and 5
Cheshire and Chester West
1-06d
Temporary use as a construction access (Work No.3A)
Work Nos 1, 2, 3, 3A, 3B, 4 and 5
Cheshire and Chester West
1-08
Temporary use as a construction compound and working area (as part of Work No.1A)
Work Nos 1, 2, 3, 4 and 5
Cheshire and Chester West
1-16, 1-17
Temporary use as construction access (as part of Work No.3)
Work Nos 1, 2, 3, 4 and 5
Cheshire and Chester West
2-02
Temporary use as a construction working area and for access to facilitate construction (as part of Work No.5C)
Work Nos 2, 3, 4 and 5
Cheshire and Chester West
2-04
Temporary use as a construction access (as part of Work No.5C)
Work Nos 2, 3, 4, 5 and 6
Cheshire and Chester West
2-07
Temporary use as a construction access (as part of Work No.5A)
Work Nos 2, 3, 4, 5 and 6
Cheshire and Chester West
2-11, 2-12
Temporary use a construction access (as part of Work No.5B)
Work Nos 2, 3, 4, 5 and 6
Cheshire and Chester West
3-01
Temporary use as a construction access (Work No. 6C)
Work Nos 4, 5, 6, 7 and 11
Cheshire and Chester West
3-02
Temporary use as a construction compound and working area (as part of Work No. 6B)
Work Nos 4, 5, 6, 7, 11, 57A and 57B
Cheshire and Chester West
4-01, 4-02
Temporary use as a construction compound and working area (as part of Work No. 6B)
Work Nos 4, 5, 6, 7, 11, 57A and 57B
Cheshire and Chester West
4-03, 4-04
Temporary use for a construction access including visibility splay (as part of Work No. 6D)
Work Nos 4, 5, 6, 7, 11, 57A and 57B
Cheshire and Chester West
4-11
Temporary use as a construction access (Work No. 6E)
Work Nos 4, 5, 6, 7, 11, 57A and 57B
Cheshire and Chester West
5-03, 5-04
Temporary use as a construction access (as part of Work No 12)
Work Nos 11, 12, 13, 14, 57C and 57D
Cheshire and Chester West
5-19, 5-21, 5-24, 5-25, 5-26, 6-11, 6-13
Temporary use for access and peat storage
Work Nos 13, 13A, 14, 57E and 57F
Cheshire and Chester West
6-20
Temporary use as a construction compound and working area (as part of Work No. 15A)
Work Nos 14, 15 and 16
Cheshire and Chester West
6-21
Temporary use as a construction access (Work No.15B)
Work Nos 14, 15 and 16
Cheshire and Chester West
7-02, 7-02a, 7-03b
Temporary use as a construction access (Work No.16B)
Work No. 16A
Cheshire and Chester West
7-10
Temporary use as a working area (as part of Work No. 17)
Work No. 17
Cheshire and Chester West
8-02
Temporary use as a construction working are and access (Work No. 18A)
Work Nos. 17, 18, 19, 19A, 20 and 21
Cheshire and Chester West
8-06, 8-08
Temporary use as a construction working area (Work No. 18)
Work Nos. 18, 19, 19A, 20 and 21
Cheshire and Chester West
8-09
Temporary use as a construction access, compound and working area (Work Nos.19A and 19B)
Work Nos. 17, 18, 19, 19A, 20 and 21
Cheshire and Chester West
8-14
Temporary use as a construction access (Work No. 19C)
Work Nos. 20 and 21
Cheshire and Chester West
9-02, 9-05, 9-06, 9-08, 9-11, 9-13
Temporary use as a construction access and working area (as part of Work No. 22)
Work Nos. 19, 22, 23, 24 and 57G
Cheshire and Chester West
9-18
Temporary use as a construction access (Work No. 23A)
Work Nos. 19, 22, 23 and 24
Cheshire and Chester West
9-20
Temporary use as a construction access and working area (as part of Work No. 23B)
Work Nos. 22, 23 and 24
Cheshire and Chester West
9-23
Temporary use as a construction access (as part of Work No.24A)
Work Nos. 24 and 25
Cheshire and Chester West
10-04a
Temporary possession for traffic management
Work No. 25
Cheshire and Chester West
10-14 10-15
Temporary use as a construction access (as part of Work No.25)
Work Nos. 25, 26, 27, 28
Cheshire and Chester West
10-17
Temporary use as a construction access (Work No.28A)
Work Nos. 25, 26, 26A, 27, 28, 28A, 28B
Cheshire and Chester West
10-19
Temporary use as a construction access and working area (as part of Work Nos.25, 26, 26A and 27
Work Nos. 25, 26, 26A, 27 and 28
Cheshire and Chester West
11-01, 11-02
Temporary use as a construction access (Work No.28A)
Work Nos. 25, 26, 26A, 27, 28, 28A, 28B
Flintshire
12-12a, 12-13
Temporary use as a construction compound and working area (as part of Work Nos. 29A and 30A)
Work Nos. 28, 29. 29A, 30 and 30A
Flintshire
12-15, 12-16, 12-17
Temporary use as a construction access (Works No.30 and 30A)
Work Nos. 28, 29, 29A, 30 and 30A
Flintshire
13-14, 13-16
Temporary use as a construction compound and working area (as part of Work No. 30D)
Work Nos. 30 and 31
Flintshire
13-19
Temporary use as a construction access (as part of Work No.30E)
Work Nos. 30 and 31
Flintshire
14-01
Temporary use as a construction compound and working area (as part of Work No. 30D)
Work Nos. 30 and 31
Flintshire
14-14
Temporary use as a construction compound and working area (as part of Work Nos. 31A and 31B)
Work Nos. 30, 31, 32 and 33
Flintshire
14-23, 14-24, 14-25, 14-26, 14-27
Temporary use as a construction access and working area (as part of Work No. 31B)
Work Nos. 30, 31, 31A, 32 and 33
Flintshire
14-30a, 15-01a
Temporary use as a construction access (as part of Work No.33)
Work No. 33
Flintshire
15-02
Temporary use as a construction access and working area (as part of Work No.33)
Work Nos.32, 33 and 33A
Flintshire
16-01, 16-06, 16-06a, 16-07, 16-08, 16-09, 16-11
Temporary use as a construction access and working area, and for diversion of public right of way and watercourse (as part of Work No. 34)
Work Nos. 33 and 34
Flintshire
16-17
Temporary use as a working area (as part of Work No. 34)
Work Nos. 34 and 35
Flintshire
16-28
Temporary use as a construction working area and access (Work No.35)
Work Nos. 35, 36, 36A and 37
Flintshire
17-05
Temporary use as a construction access and working area (as part of Work Nos. 35 and 36A)
Work Nos. 35, 36, 36A and 37
Flintshire
17-09, 17-10
Temporary use as a construction access (Work No.38A)
Work Nos. 35, 36, 36A and 37
Flintshire
17-11
Temporary use as a working area (as part of Work No. 38)
Work Nos. 37 and 38
Flintshire
17-16
Temporary use as a construction working area and access (as part of Work No.39B)
Work Nos. 38, 39, 40 and 57H
Flintshire
17-31
Temporary use as a construction access (Work No.39A)
Work Nos. 39, 40 and 57H
Flintshire
17-35, 17-37, 17-38
Temporary use as a construction access and working area (Work No. 40A)
Work Nos. 39, 40 and 57H
Flintshire
18-01
Temporary use as a working area, access and public right of way diversion (as part of Work No. 40B)
Work Nos.40, 41 and 57I
Flintshire
18-13
Temporary use as a construction compound, working area and access (as part of Work Nos. 41A and 41B)
Work Nos. 40, 41, 42 and 57I
Flintshire
18-16, 18-17
Temporary use as a construction access and visibility splay (as part of Work No.41B)
Work Nos. 40, 41, 42 and 57I
Flintshire
19-04c
Temporary use as a working area (as part of Work No. 43D)
Work Nos. 42, 43, 57J and 57K
Flintshire
20-07
Temporary use as a working area (as part of Work No. 44)
Work Nos. 44 and 57L
Flintshire
20-10, 20-10a
Temporary use as a construction access (as part of Work No.44B)
Work Nos. 44, 44A, 45, 46, 57L and 57M
Flintshire
20-16, 20-17
Temporary use as a construction access (as part of Work No.46)
Work Nos. 44, 44A, 45 and 46
Flintshire
20-19b
Temporary use as a construction access (as part of Work No.45)
Work Nos. 44, 45 and 45B
Flintshire
20-20
Temporary use as a construction compound and working area (as part of Work Nos. 44C and 45A)
Work Nos. 44, 44A, 45, 46, 57L and 57M
Flintshire
21-03
Temporary use as a construction access (Work No.47A)
Work No. 47
Flintshire
21-07
Temporary use as a construction access (Work No.47B)
Work No. 47 and 48
Flintshire
22-02
Temporary use as a working area and access (as part of Work No. 47)
Work Nos. 47 and 48
Flintshire
22-04
Temporary use for and to construct an access (Work No.49)
Work No. 47, 48 and 49
Flintshire
25-03, 25-07, 25-08, 25-09
Temporary use as a working area (as part of Work Nos. 51a, 51B and 52)
Work Nos. 51, 51A and 52
Flintshire
27-02, 28-01
Temporary use as a working area (as part of Work Nos. 53A and 53B)
Work Nos. 53, 53A and 54
Flintshire
28-02
Temporary use for and to construct an access (Work No.54)
Work Nos. 53, 53A and 54
Flintshire
29-01
Temporary use for and to construct an access (Work No.56)
Work Nos. 55, 55A and 56
Flintshire
29-02
Temporary use as a working area (as part of Work No. 55B)
Work Nos. 55, 55A and 56
Flintshire
29-06
Temporary use as a working area (as part of Work Nos. 55A and 55B)
Work Nos. 55, 55A and 56

---
Source: https://www.legislation.gov.uk/uksi/2024/436/schedule/7/part/1 (the official version)
Page: https://openlegislation.uk/hynet-carbon-dioxide-pipeline-order-2024/schedule-7/part-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.