# The Immingham Open Cycle Gas Turbine (Amendment) (No. 3) Order 2025, Article 9: Amendment to Schedule 11 (documents and plans to be certified)


In Schedule 11 (documents and plans to be certified) Table 8 is omitted and replaced with the following—
“
Table 8
(1)
Document name
(2)
Document reference
(3)
Revision number
(4)
Date
access and rights of way plans
4.4
4 (sheets 1, 2 and 3)
5 (key plan and sheet 4)
1 November 2019
book of reference
3.5
4
1 November 2019
supplemental book of reference
3.1a
1
26 February 2025
commitments registers
6.4.32
1
April 2019
environmental statement
Volume 1, 6.2
Volume 2, 6.3
Volume 3, 6.4
1
1
1
April 2019
flood risk assessment
6.4.26
1
April 2019
Framework biodiversity enhancement and management plan
6.4.17
1
April 2019
Framework construction environmental management plan
6.4.3
1
April 2019
framework construction traffic management plan
6.4.7
1
April 2019
framework construction worker travel plan
6.4.6
1
April 2019
framework written scheme of investigation
6.4.31
2
October 2019
indicative lighting strategy
5.6
1
April 2019
land plans
4.2
1 (sheets 1, 2 and 3)
2 (key plan and sheet 4)
3 (sheets 1, 2, 3 and 4, and inset sheet 1a)
1 November 2019 (key plan and sheet 4)
27 March 2019 (sheets 1 and 3)
28 March 2019 (sheet 2)
3 March 2025
(sheet 2)
4 March 2025 (sheets 1, 3 and 4, and inset sheet 1a)
works plans
4.3
1 (sheets 1, 2 and 3)
4 (sheets 4, 5 and 6)
April 2019
March 2025
statement to inform appropriate assessment
7.17
2
October 2019
”

---
Source: https://www.legislation.gov.uk/uksi/2025/622/article/9 (the official version)
Page: https://openlegislation.uk/immingham-open-cycle-gas-turbine-amendment-no-3-order-2025/article-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.