Work No. 4 – gas connection, being works for the transport of natural gas to Work No. 1, comprising—
(a) an underground and overground gas pipeline up to 600 millimetres (nominal internal diameter);
(b) cathodic protection system and posts;
(c) marker posts; and
(d) control systems and cables.

---