# The Immingham Open Cycle Gas Turbine Order 2020, Paragraph 121

Extent: E+W

Before commencing any part of the authorised development which would have an effect on the operation or maintenance of the pipeline and access to it, the undertaker must submit to Centrica plans and sections of the proposed works and such further particulars as Centrica may, within 28 days from the day on which plans and sections are submitted under this paragraph, reasonably require.

---
Source: https://www.legislation.gov.uk/uksi/2020/847/schedule/9/paragraph/121 (the official version)
Page: https://openlegislation.uk/immingham-open-cycle-gas-turbine-order-2020/schedule-9/paragraph-121
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.