Any approval of Centrica required under paragraph 123 must not be unreasonably withheld or delayed but may be given subject to such reasonable requirements as Centrica may require to be made for—
(a) the continuing safety and operational viability of the pipeline; and
(b) the requirement for Centrica to have uninterrupted and unimpeded access to the pipeline at all times.

---