(1) Insofar as the construction of the OCGT authorised development is or may be undertaken concurrently with the Able authorised development, the undertaker must—
(a) co-operate with Able with a view to ensuring—
(i) the co-ordination of construction programming and the carrying out of works; and
(ii) that access for the purposes of constructing the respective authorised developments is maintained for the undertaker and Able and their respective contractors; and
(b) use reasonable endeavours to avoid any conflict arising from the carrying out of the respective authorised developments.

---