# The Immingham Open Cycle Gas Turbine Order 2020, Paragraph 137

Extent: E+W

Before commencing any part of the authorised development which would have an effect on the operation or maintenance of the pipelines and access to them, the undertaker must submit to TLOR plans and sections of the proposed works and such further particulars as TLOR may, within 28 days from the day on which plans and sections are submitted under this paragraph, reasonably require.

---
Source: https://www.legislation.gov.uk/uksi/2020/847/schedule/9/paragraph/137 (the official version)
Page: https://openlegislation.uk/immingham-open-cycle-gas-turbine-order-2020/schedule-9/paragraph-137
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.