# The Immingham Open Cycle Gas Turbine Order 2020, Paragraph 182

Extent: E+W

If Northern Powergrid at any time becomes aware that an estimate agreed is likely to be exceeded, it must forthwith notify the undertaker and must submit a revised estimate of the relevant costs and expenses to the undertaker for agreement.

---