# The Immingham Open Cycle Gas Turbine Order 2020, Paragraph 189: Protection of Hornsea 1 from works

Extent: E+W

(1) Before any works are commenced the undertaker must submit to Hornsea 1 plans and sections of the proposed works and such further particulars as Hornsea 1 may, within 14 days from the day on which plans and sections are submitted under this paragraph, reasonably require.
(2) The undertaker must not commence any works to which sub-paragraph (1) applies until Hornsea 1 has given written approval of the plan so submitted.
(3) Any approval of Hornsea 1 required under sub-paragraph (2)—
(a) may be given subject to reasonable conditions; and
(b) must not be unreasonably withheld.

---
Source: https://www.legislation.gov.uk/uksi/2020/847/schedule/9/paragraph/189 (the official version)
Page: https://openlegislation.uk/immingham-open-cycle-gas-turbine-order-2020/schedule-9/paragraph-189
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.