# The Immingham Open Cycle Gas Turbine Order 2020, Paragraph 195: Acquisition of land

Extent: E+W

Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference to the Order, the undertaker may not appropriate or acquire or take temporary possession of any land interest or appropriate, acquire, extinguish, interfere with or override any easement, other interest or right and/or cables of Hornsea 2 other than by agreement, such agreement not to be unreasonably withheld.

---
Source: https://www.legislation.gov.uk/uksi/2020/847/schedule/9/paragraph/195 (the official version)
Page: https://openlegislation.uk/immingham-open-cycle-gas-turbine-order-2020/schedule-9/paragraph-195