# The Immingham Open Cycle Gas Turbine Order 2020, Paragraph 33: Notices

Extent: E+W

The plans submitted to National Grid by the undertaker pursuant to paragraphs 25(1) and 26(1) must be sent to National Grid Plant Protection at plantprotection@nationalgrid.com or such other address as National Grid may from time to time appoint instead for that purpose and notify to the undertaker in writing.

---
Source: https://www.legislation.gov.uk/uksi/2020/847/schedule/9/paragraph/33 (the official version)
Page: https://openlegislation.uk/immingham-open-cycle-gas-turbine-order-2020/schedule-9/paragraph-33
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.