  "text": "Where the existing gas pipeline crosses below... a ditch or stream it will be protected by a concrete slab and the pipe will be located at such a depth so as to provide at least 1.1 metres cover from the true cleaned bottom of the ditch or stream to the top of the pipe. All ditches, open drains or watercourses interfered with by the exercise of the specified rights will be maintained in effective condition during works by the undertaker and restored to as good a condition as before the commencement of the works.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Sch. 9 para. 81 full stop omitted (17.5.2021) by virtue of The Immingham Open Cycle Gas Turbine (Correction) Order 2021 (S.I. 2021/581), art. 1, Sch."
    },
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 9 para. 81 in force at 1.9.2020, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2020/847/schedule/9/paragraph/81",
    "retrieved_at": "2026-10-28T22:26:59.097041+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}