(1) The undertaker must ensure that the existing gas pipeline is cathodically protected against corrosion and any buildings and structures within HOR likely to be affected will be suitably protected provided reasonable facilities are given by P66 for this to be done.
(2) Sub-paragraph (1) does not require the undertaker to do anything in respect of pipes, cables or like apparatus or any building or structure laid or constructed after the existing gas pipeline was first laid.

---