# The Infrastructure Consent (Compulsory Acquisition) (Wales) Regulations 2025, Regulation 23: Determination of procedure where an application is varied to include a compulsory acquisition request for additional land

Extent: E+W

The examining authority must determine the procedure for the examination of an application that has been varied under these Regulations, by the latest of—
(a) the end of the 28 days specified in regulation 10(1) of the 2025 Examination Regulations (determination of procedure), or
(b) the end of 21 days beginning with the day specified for the purpose of regulation 20(5)(m).

---
Source: https://www.legislation.gov.uk/wsi/2025/691/regulation/23 (the official version)