Regulation 6 Notice of proposed application
An applicant must notify the Welsh Ministers of a proposed application (“notice of proposed application”).
A notice of proposed application must contain the following information—
the reference number of the relevant infrastructure consent order,
a statement confirming whether the proposed application is to change or revoke an infrastructure consent order,
where the proposed application is to change an infrastructure consent order—
a description of the change, and
where the proposed application includes a compulsory acquisition request, a statement to that effect,
where the proposed application is to revoke an infrastructure consent order—
where the applicant is a planning authority, a statement explaining how the authority considers the conditions in section 90(4) of the 2024 Act are met;
in any other case, a statement giving reasons for the proposed application, and
where the proposed application relates to EIA development, a statement to that effect.
A notice of proposed application must be accompanied by—
any documents, plans or other information that are relevant to the proposed application, and
any fee required to be paid in relation to the giving of the notice.