# The Infrastructure Consent (Miscellaneous Provisions) (Wales) Regulations 2025, Regulation 12: Pre-application meetings

Extent: E+W

(1) A developer may make a written request for a pre-application meeting with a planning authority, Natural Resources Wales or the Welsh Ministers (as the case may be).
(2) Where a planning authority, Natural Resources Wales or the Welsh Ministers (as the case maybe) receive a request for a pre-application meeting, they must give notice to the person who made the request, within 15 days of the day on which the request is received, confirming whether or not a meeting will be held.

---