# The Infrastructure Consent (Miscellaneous Provisions) (Wales) Regulations 2025, Paragraph 8


Installation of an electric line above ground associated with a generating station in Wales or the Welsh marine area with a nominal voltage of 132 Kilovolts or less, with a length less than 2 kilometres (to the extent it is in Wales).

---
Source: https://www.legislation.gov.uk/wsi/2025/887/schedule/1/paragraph/8 (the official version)
Page: https://openlegislation.uk/infrastructure-consent-miscellaneous-provisions-wales-regulations-2025/schedule-1/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.