# The Infrastructure Consent (Pre-Application and Application Procedure and Transitional Provisions) (Wales) Regulations 2025, Regulation 25: Publicity for valid applications: website

Extent: E+W

Where the Welsh Ministers accept an application as a valid application, they must publish the following information on a website maintained by them or on their behalf—
(a) the location of the proposed development,
(b) a description of the proposed development,
(c) where and when the application may be inspected,
(d) how representations may be made in relation to the application,
(e) the date by which representations are to be received,
(f) in the case of an application accompanied by an environmental statement, the fact that the proposed development is subject to an EIA procedure and—
(i) how copies of the environmental statement may be obtained, and
(ii) the fee for obtaining copies of the environmental statement,
(g) in accordance with the requirements of the Freedom of Information Act 2000 and the Data Protection Act 1998, the main reports and advice issued to the Welsh Ministers at the time the information is published (if any),
(h) details of the arrangements for public participation in the decision-making procedure,
(i) the procedure and publication of any new information subsequently submitted by the applicant, and
(j) any other information relevant to an application which only becomes available after the time all other information is published.

---
Source: https://www.legislation.gov.uk/wsi/2025/690/regulation/25 (the official version)
Page: https://openlegislation.uk/infrastructure-consent-pre-application-and-application-procedure-and-transitional-provisions-wales-regulations-2025/regulation-25
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.