# The Infrastructure Consent (Pre-Application and Application Procedure and Transitional Provisions) (Wales) Regulations 2025, Regulation 9: Consultation and publicity for development in Wales: additional requirements

Extent: E+W

The applicant must publicise the proposed application by the following methods—
(a) by publication of the notice in a newspaper circulating in the locality in which the land to which the proposed application relates is situated for a minimum period of 7 days, and
(b) by holding at least one public engagement event in the locality of the land to which the application relates.

---