# The Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009, Regulation 10: Certifying compliance with section 56 of the Act

Extent: E+W+S

(1) The form prescribed for the purposes of section 58(2) (certifying compliance with section 56 of the Act) is the form set out in Schedule 3 to these Regulations.
(2) Within the period of 10 working days immediately following the deadline set under regulation 9(4), the applicant must send to the Secretary of State—
(a) the certificate of compliance in the form mentioned in paragraph (1); and
(b) where the applicant applies for an order granting development consent which includes a request to authorise compulsory acquisition of land or of an interest or right over land, a notice of persons interested in the land to which that request relates, in the form set out in Schedule 4 to these Regulations.

---
Source: https://www.legislation.gov.uk/uksi/2009/2264/regulation/10 (the official version)
Page: https://openlegislation.uk/infrastructure-planning-applications-prescribed-forms-and-procedure-regulations-2009/regulation-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.