# The Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011, Regulation 42: Completion of examination

Extent: E+W+S

(1) When the Examining body has completed its examination of the application, it must inform each interested party of that fact.
(2) The Examining body must complete its examination of the application by the end of the period of 4 months beginning with the day after the start day.
(3) The start day is the day on which the meeting required by regulation 28 is held or, if that meeting is held on 2 or more days, the later or latest of those days.
(4) The Secretary of State may set a date for a deadline under this regulation that is later than the date for the time being set.
(5) The Secretary of State may change the date set for the deadline under paragraph (4)—
(a) more than once in relation to the same deadline;
(b) after the date for the time being set for the deadline.
(6) Where the Secretary of State has changed the date set for the deadline the Secretary of State must—
(a) notify each interested party of the new deadline; and
(b) publicise the new deadline in such a manner as the Secretary of State thinks appropriate.

---
Source: https://www.legislation.gov.uk/uksi/2011/2055/regulation/42 (the official version)
Page: https://openlegislation.uk/infrastructure-planning-changes-to-and-revocation-of-development-consent-orders-regulations-2011/regulation-42
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

