(1) The undertaker may construct the railway so as to carry it on the level across the highways specified in Schedule K.
(2) The undertaker may in constructing any new level crossing alter the level of any highway specified in Schedule K.
(3) The highway authority and the undertaker may enter into agreements with respect to the construction and maintenance of any new level crossing; and such an agreement may contain such terms as to payment or otherwise as the parties consider appropriate.
(4) In this article—
“new level crossing” means the place at which the railway is authorised by this article to cross a highway on the level; and
“the railway” means the railway authorised to be constructed by this Order.

---
Source: https://www.legislation.gov.uk/uksi/2009/2265/schedule/2/paragraph/18 (the official version)
Page: https://openlegislation.uk/infrastructure-planning-model-provisions-england-and-wales-order-2009/schedule-2/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.