Article 4 Power to deviate

Original text. Later amendments are not shown.

(1)

In constructing or maintaining any of the scheduled works, the undertaker may—

(a)

deviate laterally from the lines or situations shown on the works plans within the limits of deviation and in particular the marine feeder cables may commence by a connection within the limits of deviation with any of the wind turbines; and

(b)

deviate vertically from the levels shown on the sections—

(i)

in respect of the top of the wind turbines and subject to paragraph 2, to any extent not exceeding 50 metres downwards;

(ii)

in respect of the depth of the piled foundations of the turbines into the seabed, to any extent upwards and to any extent not exceeding 10 metres downwards;

(iii)

in respect of the inter-turbine cables to any extent not exceeding 5 metres downwards;

(iv)

in respect of the marine feeder cables, from their point of commencement to a point 500 metres from the level of high water to any extent not exceeding 5 metres downwards; and

(v)

in respect of the marine feeder cables, from the second point mentioned in paragraph (1)(b)(iv) to their point of termination to any extent not exceeding 20 metres downwards.

(2)

There shall be a minimum distance of 22 metres between the lowest point of the rotating blades of the wind turbines and the level of high water.