# The Inverness Harbour Revision (Works) Order 2005, Article 3: Power to construct works


(1) Subject to the provisions of this Order, the Trustees may, in Inverness and in the situations and lines and within the limits of deviation and according to the levels shown on the deposited plan and section, construct and maintain the works hereinafter described, together with all necessary and proper works and conveniences connected with or incidental thereto, that is to say:–
Work No. 1
A reclamation of 9.8 hectares of foreshore of the river Ness north east of the existing harbour at Longman Quay, Inverness, the formation of a quay wall of sheet steel piling extending some 180 metres in length to the north east, the dredging and formation of a marina facility for up to 100 berths and the provision of storage facilities, the infilling of the existing yacht haven and the formation of a rock armour bunds to protect the works.
Work No. 2
An extension of Carnarc Point on the north west shore of the river Ness by 70 metres to form a breakwater to protect works in Work No. 1.
(2) The Trustees may within the limits of deviation reconstruct, renew, enlarge or alter temporarily or permanently the works.

---
Source: https://www.legislation.gov.uk/ssi/2005/489/article/3 (the official version)
Page: https://openlegislation.uk/inverness-harbour-revision-works-order-2005/article-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.