# The Ipswich Barrier Order 2012, Schedule 4: ACQUISITION OF NEW RIGHTS ONLY

Extent: E+W+S

(1)
(2)
Number of land shown on land plans
Purpose for which new rights may be acquired
1b, 2aa, 2af, 2b, 4a, 4b and 5a.
Flood wall and gate
2ah, 2al,2ad, 2m, 2n, 2t, 2w and 6b.
Diversion of existing132kV electricity cable (Work No.3)
2e and 4e.
Landscaping
2j, 2k and 2l.
Access, maintenance and crane oversailing
2q
Access to new control building (Work No. 2)

---