# The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, Article 12: Access to works

Extent: E+W+S

(1) The undertaker may, for the purposes of the authorised development—
(a) form and lay out the permanent means of access, or improve existing means of access, in the locations specified in Schedule 4 (streets subject to permanent alteration of layout);
(b) with the approval of the relevant planning authority after consultation with the highway authority, form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised development.
(2) If a highway authority fails to notify the undertaker of its decision within 28 days of receiving an application under paragraph (1) or refuses approval without giving any grounds for its refusal that highway authority is deemed to have granted approval.

---
Source: https://www.legislation.gov.uk/uksi/2022/1396/article/12 (the official version)