# The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, Paragraph 25: Lighting

Extent: E+W+S

The undertaker must provide and maintain at its own expense in the vicinity of the specified or protective works such temporary lighting and such signal lights for the control of navigation as the engineer may reasonably require during the construction or failure of the specified or protective works.

---
Source: https://www.legislation.gov.uk/uksi/2022/1396/schedule/10/paragraph/25 (the official version)