# The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, Paragraph 78: Carbon dioxide export connections works

Extent: E+W+S

Without limiting any other provision of this Order, where NGC proceeds to carry out Work No.7B or any part of it, the undertaker must use its reasonable endeavours to facilitate the programming, execution, commissioning and future operation and maintenance of those works in a safe, efficient and economic manner alongside any other part of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2022/1396/schedule/10/paragraph/78 (the official version)