# The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, Schedule 12: DOCUMENTS AND PLANS TO BE CERTIFIED

Extent: E+W+S

Table 8
(1) Document Name
(2) Document Reference
Access and rights of way plans
4.4
Book of reference
3.1
Land plans
4.2
Works plans
4.3
Combined heat and power assessment
5.7
Environmental statement
6.0, 10.6-10.9
Design principles statement (appendix 1 of the design and access statement)
5.6 (appendix 1)
Flood risk assessment
6.3.20
Outline written scheme of investigation
7.4
Indicative landscape and biodiversity plan
4.15
Landscaping and Biodiversity Management and Enhancement plan
5.10
Indicative surface water drainage plan
4.13
Framework construction environmental management plan
7.1
Framework construction traffic management plan
7.2
Framework construction workers travel plan
7.3
Indicative lighting strategy
5.11
Haul road plans
4.19
Pilfrey laydown plans
4.20
Application guide
1.2

---
Source: https://www.legislation.gov.uk/uksi/2022/1396/schedule/12 (the official version)
Page: https://openlegislation.uk/keadby-3-carbon-capture-equipped-gas-fired-generating-station-order-2022/schedule-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.