# The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, Paragraph 9: Pre-construction

Extent: E+W+S

Not later than 8 weeks prior to the proposed commencement of licences activities the undertaker must submit to the MCA and the MMO for review and approval in writing by the MMO the CEMP covering the period of construction to include details of—
(a) a marine pollution contingency plan to address the risks, methods and procedures to deal with any spills and collision incidents of the authorised development in relation to all activities to be carried out;
(b) a biosecurity plan detailing how risk of the introduction and spread of invasive non-native species will be minimised; and
(c) waste management and disposal arrangements.
The authorised development must be undertaken in accordance with the CEMP, unless otherwise agreed in writing by the MMO.

---
Source: https://www.legislation.gov.uk/uksi/2022/1396/schedule/13/paragraph/9 (the official version)
Page: https://openlegislation.uk/keadby-3-carbon-capture-equipped-gas-fired-generating-station-order-2022/schedule-13/paragraph-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.