# The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, Paragraph 10: Site security

Extent: E+W+S

(1) No part of the authorised development may be brought into use until a written scheme detailing security measures to minimise the risk of crime has, for that part, been submitted to and approved by the relevant planning authority.
(2) The approved scheme must be implemented and maintained throughout the operation of authorised development.

---