# The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, Paragraph 11: Fire prevention

Extent: E+W+S

(1) No part of Work Nos. 1 or 8 may commence until details of the specification and location of accesses for the use of all fire appliances in all of the major building structures and storage areas within the authorised development has, for that part, been submitted to and approved by the relevant planning authority.
(2) The authorised development must be implemented in accordance with the approved details and all relevant accesses must be maintained to the reasonable satisfaction of the relevant planning authority at all times throughout the operation of the authorised development.

---
Source: https://www.legislation.gov.uk/uksi/2022/1396/schedule/2/paragraph/11 (the official version)
Page: https://openlegislation.uk/keadby-3-carbon-capture-equipped-gas-fired-generating-station-order-2022/schedule-2/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.