# The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, Paragraph 30: Piling and penetrative foundation design

Extent: E+W+S

(1) No part of the authorised development comprised within Works Nos. 1, 2, 4A, 4B, 7, 8B or 9B may commence, save for the permitted preliminary works, until a written piling and penetrative foundation design method statement, informed by a risk assessment, for that part, has been submitted to and, after consultation with the Environment Agency, approved by the relevant planning authority.
(2) All piling and penetrative foundation works must be carried out in accordance with the approved method statement unless otherwise agreed with the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2022/1396/schedule/2/paragraph/30 (the official version)
Page: https://openlegislation.uk/keadby-3-carbon-capture-equipped-gas-fired-generating-station-order-2022/schedule-2/paragraph-30
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.